Retain a qualified consultant with qualifications equal to Ms. Hersey's to evaluate 4 options:
- 5-year withdrawal from the All requirements Project to a Contract Rate of Delivery agreement, followed by a 3-year complete withdrawal from the CRD contract and the outright sale of our generation and distribution assets.
- 5-year withdrawal from the ARP to a CRD, followed by the sale or lease or our generation- assets while maintaining our distribution system, the city would purchase 100% of its power either from the new owner of our power plant or through other purchase power contracts.
- 5-year withdrawal from the ARP to a CRD, the City maintains its generation and upgrades it, while continuing to buy some power through purchased power contracts--basically the City lives on its own, stays a member of FMPA, not a member of ARP, and the city would continue to operate the way it used to operate before it joined ARP.
- Any other option Ms. Hersey wanted to submit