ROLO President reports on 6th Avenue Bridge Construction

6th Avenue south night road construction

There was a meeting last tonight that you could call into concerning the nighttime construction on 6th Ave South. Here are some facts from the meeting:

Why night construction?

  • The construction cannot be done within so many feet of a live power pole.
  • The Lake Worth lines near the construction zone have to be de-energized for work to continue.
  • Lake Worth can re-route the power load so that residents will not lose power but this can only be done at night.
  • Night construction will start August 7th and go until August 19th, Monday to Friday,10PM to 10 AM. Not on weekends.
  • The noise and vibrations should be negligible, but there will be an engineer on site monitoring this at all times.
If you have further questions you may call 561-684-4012

Katie McGiveron, President of ROLO