Manhole work in Lake Worth

Start Date: August 2015

The City of Lake Worth Department of Water Utilities is working with Lanzo Lining Services, Inc. performing structural lining of existing 15” Sanitary Sewer pipe on

Fordham Drive | Aug 21 - Sept 16
6th Ave South | Aug 24 - Oct 1
15th Ave South | Aug 24 - Oct 1

The contractor will be working in the Westbound curb lane of the roadway from Manhole. to Manhole. There will be minimal inconvenience to the residents in the area.